SAT & Commissioning Checklist
Shared by TSIMEREZIVO Team · 4 Oct 2026 · 58 views
# SAT & Commissioning Checklist Template
Project: ______________ Site: ______________ SAT No: SAT-____
Date: ______________ System: ______________ Rev: __
## 1. Purpose
Demonstrate the installed system works in the real plant environment —
the FAT proved the panel; the SAT proves the process.
## 2. Prerequisites
- [ ] All FAT punch items (Cat A/B) closed
- [ ] Loop checks 100% complete and signed
- [ ] Instruments calibrated and certificated
- [ ] Cable megger/continuity records filed
- [ ] Software version = FAT-approved version (record hash/build)
- [ ] As-built drawings issued for construction
- [ ] Permit to work / LOTO procedures agreed
- [ ] Operations team briefed on test scope
## 3. Installation verification
- [ ] Panel earthing: <1 Ω instrument earth, separate from power earth
- [ ] Cable glands, segregated trays, screen termination per spec
- [ ] Instrument impulse lines leak-tested
- [ ] Environmental: temperature/dust/humidity within panel rating
## 4. Loop checks (per instrument index)
For each loop record: injected/measured value → SCADA value → PASS/FAIL.
- [ ] Analog loops end-to-end (field → marshalling → I/O → HMI)
- [ ] Digital: field contact → correct tag + correct state on HMI
- [ ] Control valves: stroke test 0–25–50–75–100%, verify positioner
- [ ] HART/smart variables reading correctly
## 5. Process functional tests
- [ ] Interlocks on live signals (bypass register controlled + logged)
- [ ] Trip setpoints proven at the process value, not just simulated
- [ ] PID loops: step response, tune, record final P/I/D per loop
- [ ] Sequences run against real equipment with ops witnessing
- [ ] Alarms: generate one real alarm per area, verify annunciation
## 6. Integrated tests
- [ ] Utility failure recovery (power dip, air loss, network break)
- [ ] Emergency shutdown activation path — full chain, real output
- [ ] Operator handover: shifts can run the system unassisted
## 7. Documentation handover
- [ ] As-built markups returned to drafting
- [ ] Software backup taken post-SAT and stored in vault
- [ ] Loop folders complete: certs, loop checks, datasheets
- [ ] Training records signed
## 8. Punch list & sign-off
| # | Item | Category | Owner | Closed |
|---|---|---|---|---|
| 1 | | | | |
SAT PASSED / CONDITIONAL / FAILED — circle one.
Conditional pass requires a dated action plan signed by client + vendor.